KUALA LUMPUR, 25 November 2026 — The government is carrying out three immediate flood-mitigation works in Shah Alam, with construction due to be finished between February and March next year, and has approved a larger RM40 million project for the Sungai Rasah basin under the 13th Malaysia Plan.
Deputy Minister of Energy Transition and Water Transformation Datuk Seri Abdul Rahman Mohamad set out the plans during a Special Chamber session in the Dewan Rakyat on Wednesday, responding to a question from Azli Yusof, the Member of Parliament for Shah Alam, about flood control in the basin after recent flash floods.
The first of the short-term projects is a flood wall and flap gate at Taman Rashna, costing RM350,000 and scheduled for completion on March 17, 2027, Abdul Rahman said, according to Bernama, as reported by Malay Mail. The second involves an outlet structure, a flap gate and a flood wall near the Bukit Raja junction, costing RM199,000, with completion due on February 17, 2027. The third is a flood wall at Taman Intan, costing RM200,000, also scheduled for completion on February 17, 2027.
The Selangor Department of Irrigation and Drainage has also deployed six mobile pump units at four high-risk sites — Taman Rashna, Taman Intan, the area near the Bukit Raja junction, and the AEON supermarket — to speed the drainage of floodwater and shorten the time it stands in those neighbourhoods, he said.
A longer-term plan for Sungai Rasah
For the longer term, Abdul Rahman said the government has approved RM40 million under the First Rolling Plan of the 13th Malaysia Plan for a water control gate at the estuary of the Sungai Rasah, together with a pump house, a flood retention basin and riverbank retaining walls.
That project is still at the preliminary design stage. Physical works are targeted to start in the second quarter of 2028 and to finish by 2031. The ministry has also proposed splitting the RM40 million allocation into two separate tenders, which he said could shorten the construction period and bring completion forward to 2029.
A key aim, he said, would be to stop water from the Sungai Klang overflowing into high-risk parts of Shah Alam. That component is estimated to cost between RM15 million and RM20 million, depending on the final scope and the findings of technical studies.
“Overall, the planning for these components aims to enhance the capacity of the flood control system in the Sungai Rasah Basin, making it more integrated and effective,” he said. “These measures are expected to reduce the risk and impact of flooding on residents and the surrounding areas; however, the final scope of the project remains subject to the results of studies and detailed designs prepared by the consultants.”
Shah Alam, Selangor’s state capital, has a long record of sudden flooding, particularly in low-lying neighbourhoods along the Sungai Rasah and in areas affected when the Sungai Klang overtops its banks. Taman Sri Muda, in Section 25, was among the worst-hit parts of the city in the December 2021 floods, and residents have repeatedly pressed for more lasting engineering works rather than short-term pumping after each downpour.
The three immediate projects are modest in cost compared with the RM40 million basin plan, and are meant to offer some relief before the larger works begin. Even on the accelerated timetable described by the deputy minister, the main control gate, pump house and retention basin would not be completed before 2029. The ministry’s figures also remain subject to detailed design, so the final cost and scope could still change.
Abdul Rahman’s statement was delivered as parts of the country continue to deal with the northeast monsoon, which typically brings heavy rain and flooding to several states between November and March. The short-term works in Shah Alam are scheduled to be finished in the first quarter of 2027, before the following year’s monsoon season is well under way, while the longer-term scheme is intended to give the Sungai Rasah basin a more permanent system of gates, pumps and storage.