Source : PETRA's X
PUTRAJAYA, October 15, 2026 — Malaysia’s Ministry of Energy Transition and Water Transformation (PETRA) has handed a RM7.93 million flood mitigation project in northern Kuala Terengganu to the Terengganu state government, saying the works will give direct protection to about 3,000 residents in Gong Badak, Kuala Nerus.
The ministry restated the handover in a thread on X on November 15, 2026, with a graphic that cited a PETRA media release dated October 15, 2026. In the post, written in Malay, PETRA said the North Kuala Terengganu (UMT) and Surrounding Areas Flood Mitigation Plan, or Rancangan Tebatan Banjir (RTB), “has been fully completed and handed over to the Terengganu State Government.” An RTB is a planned drainage and flood-control scheme; in plain terms, it is meant to move stormwater away faster so that fewer homes and roads go under water after heavy rain.
The works were carried out by the Department of Irrigation and Drainage (Jabatan Pengairan dan Saliran, JPS) Malaysia. According to the X thread, the project was able to “improve the capacity of the existing drainage system and reduce the flood-risk area by about 200 hectares (from 700 hectares to 500 hectares).” That still leaves 500 hectares in the risk zone, so the scheme shrinks the exposed area rather than removing the flood threat altogether. The ministry said the initiative “provides direct protection benefits to about 3,000 residents in Gong Badak, Kuala Nerus.” The accompanying poster used similar wording, saying the completed project would “protect about 3,000 Gong Badak residents from flood risk.”
Those figures match PETRA’s official media release of October 15, 2026. The statement said the Gong Badak scheme was one of two projects handed over the same day, together worth RM145.46 million. The second was the Setiu River Mouth Conservation Project in the Setiu district, valued at RM137.53 million, which the ministry said was completed on September 1, 2026 — 50 days earlier than the original contract date of October 21, 2026. PETRA said that project is intended to strengthen the stability of the river mouth and the safety of the waterway, reduce the risk of erosion and flooding nearby, and support local fishing and tourism.
The release said the handover was completed by the director-general of JPS Malaysia, Datuk Ir. Mohamad Radzi Abdul Talib, to Terengganu’s deputy state secretary (development), Dato’ Azran Amin Mazlan, and was witnessed by PETRA secretary-general Dato’ Sri Mad Zaidi Mohd Karli and Terengganu state secretary Dato’ Mohd Azmi Mohamad Daham.
PETRA said the Federal Government, through the ministry, would continue to give priority to flood mitigation, the conservation of rivers and river mouths, and the protection of exposed areas, “to strengthen community resilience and support sustainable socio-economic development.”
What to watch is how the reduced risk in Gong Badak holds in the coming monsoon, and how the remaining 500 hectares are managed once the assets sit with the state. This announcement does not set out a maintenance timetable, or say what further works, if any, are planned for the land that is still described as flood-prone.
Sources: PETRA on X, and PETRA media release, October 15, 2026.